D.  WATER

 

 

PROJECT TITLE:   Jenks-Carpenter/Holt Road Water Line Reinforcement

 

RESPONSIBLE DEPARTMENT:   Engineering

 

PROJECT FUNDING:   $1,600,000

 

FIRST YEAR ESTIMATED OPERATING COSTS:   None

 

PROJECT DESCRIPTION:

The Jenks-Carpenter/Holt Road Water Line Reinforcement project provides for the installation of 6,100 linear feet of 36–inch water line along Holt Road between NC-55 and Jenks-Carpenter Road to reinforce the existing 36-inch water line at that location.  This project, in combination with the Holt Road to Davis Drive Water Line Connection project, will reinforce the southern side of the central pressure zone.  The FY 2010 appropriation of $1,600,000 fully funds this project.

                                                                                                                      

PROJECT JUSTIFICATION:

This project provides additional water service capacity to meet periods of peak demand and high fire fighting flow.  The Jenks-Carpenter/Holt Road Water Line Reinforcement project is growth-related and will increase the Town’s utility service area.

 